WesTech Engineering (current manufacturer of the Town’s water treatment package plant) visited the water treatment plant.  The site visit was to help assess the condition of the filter that was empty to see if it could be rehabilitated.  If the filter could be...

3/10/23

Report is available from the work completed at the Water Treatment Plant in conjunction with the City of Forsyth. View Report.

2/28/23

With the aid of Southeastern Montana Development Corporation and Great West Engineering, the Town submitted an application to the Montana Coal Board to help fund roof repairs at the Water Treatment Plant in addition to some miscellaneous equipment.

2/23/23

Report is available from the work completed at the Water Treatment Plant in conjunction with the City of Forsyth. View Report.

2/16/23

Report is available from the work completed at the Water Treatment Plant in conjunction with the City of Forsyth.  View Report.